How to Add a Custom Due Date to a Package

How to set a different due-date at a package level

1 min read

Package due dates override a project's due date (for that particular package).

You can add a due date to a package in two ways.

Option 1: When setting up a new project and inviting subcontractors

When you're at step 5 (Invitations) of setting up a new project, there is now a Due date field noted on each trade

By default it shows the project's due date. Simply type the custom package due date you want, or use the calendar pop-up, to add your own.

Option 2: After you've set up the project

  • Start by going to the Monitor Responses page for the project (for example, via the Project Dashboard)
  • In the Quick Actions menu, choose ’Invite Multiple’
  • Just like in Option 1 above, there is now a Due Date field before each trade
  • By default it shows the project's due date. Simply type the custom package due date you want, or use the calendar pop-up, to add your own.
  • You can only change a package custom due date if you issue a new invitation