How to Add a Custom Due Date to a Package

How to set a different due-date at a package level

1 min read

Package due dates override a project's due date (for that particular package).

You can add a due date to a package in two ways.

Option 1: When setting up a new project and inviting subcontractors

When you're at step 5 (Invitations) of setting up a new project, there is now a Due date field noted on each trade

By default it shows the project's due date. Simply type the custom package due date you want, or use the calendar pop-up, to add your own.

article image

Option 2: After you've set up the project

Start by going to the Monitor Responses page for the project (for example, via the Project Dashboard).

In the ’Quick Actions’ menu, choose ’Invite Multiple’.

Just like in Option 1 above, there is a now a Due date field before each trade.

By default it shows the project's due date. Simply type the custom package due date you want, or use the calendar pop-up, to add your own.

You can only change a package custom due date if you issue a new invitation.

article image

Did this answer your question?