Package due dates override a project's due date (for that particular package).
You can add a due date to a package in two ways.
Option 1: When setting up a new project and inviting subcontractors
When you're at step 5 (Invitations) of setting up a new project, there is now a Due date field noted on each trade
By default it shows the project's due date. Simply type the custom package due date you want, or use the calendar pop-up, to add your own.
Option 2: After you've set up the project
Start by going to the Monitor Responses page for the project (for example, via the Project Dashboard).
In the ’Quick Actions’ menu, choose ’Invite Multiple’.
Just like in Option 1 above, there is a now a Due date field before each trade.
By default it shows the project's due date. Simply type the custom package due date you want, or use the calendar pop-up, to add your own.
You can only change a package custom due date if you issue a new invitation.