Adding or Changing Dates on the Letting Schedule

An overview of how to add or change dates on the Letting Schedule

2 min read
  1. Adding milestone dates to an empty letting schedule
  2. Adding milestone dates where a timeframe has already been entered
  3. Updating an existing milestone date where no timeframes
  4. Updating the ‘Quotes Due’ milestone date where a timeframe has already been entered
  5. Updating the ‘Let By’ milestone date where a timeframe has already been entered
  6. Updating the "Start on Site" milestone date where a timeframe has already been entered

Adding milestone dates to your letting schedule helps minimise project delay and cost overruns.

Depending on what information has already been entered you will find adding and amending dates behaves a little differently.

Adding milestone dates to an empty letting schedule

When two dates are populated and no timeframe exists between them the timeframe will be calculated automatically.

article image

Adding milestone dates where a timeframe has already been entered

When a date is added after timeframes have been populated the remaining dates will be automatically calculated using the timeframes.

article image

Updating an existing milestone date where no timeframes

Where no timeframes exist, updating a date will have no impact on other dates or milestones.

Keep in mind, this is only the case if there are no adjacent timeframes or milestones set.

article image

Updating the ‘Quotes Due’ milestone date where a timeframe has already been entered

When the ’Quotes Due’ date is updated, the ’Let By’ and ’Start on Site’ will not be changed, however, the tender period timeframe will be adjusted to accommodate the new ’Quotes Due’ date.

article image

Updating the ‘Let By’ milestone date where a timeframe has already been entered

When the ’Let By’ date is updated, the ’Quotes Due’ date will be adjusted but the ’Start on Site’ will be unchanged. The ’Lead Time’ timeframe will be adjusted to ensure its accuracy.

article image

Updating the "Start on Site" milestone date where a timeframe has already been entered

When the ’Start on Site’ date is updated, the ’Let By’ and ’Quotes Due’ will be updated to ensure the accuracy of the ’Lead Time’’ and ’Tender Period’ timeframes.

article image