How to Revise Documents in the Procurement Phase

Learn how to use the Addendum Wizard and notify subcontractors of revisions

3 min read
  1. Importing and uploading documents
  2. Revised document upload
  3. Confirm which old documents should be replaced
  4. Confirm Packages
  5. Notify Subcontractors

We know that revisions are an essential part of your Procurement process. In this article you can learn how to:

  • Use the addendum wizard to upload revised documents
  • Notify subcontractors of any document changes relevant to their packages

Importing and uploading documents

In order to revise, you need to have an initial set of Documents in your Procurement project. You have two options here:

Revised document upload

When you want to revise your documents, head to the Documents tab from within your Procurement project

article image

  • Select 'Document Actions' and then 'Start new revision'

article image
  • You will see pop-up. Give your Addendum a Name and Description to help you and other users identify this Addendum later
  • Select 'Create Addendum' and you will land in the Addendum Wizard. You will know you are here as you will see the 3-step process outlined in the top right corner
article image

  • You will see 'NEW' next to your newly uploaded documents

article image

Confirm which old documents should be replaced

There are two ways you can confirm which old documents should be replaced by the new versions - auto-suggested or manually.

Auto-suggested revisions

Using auto-revisions will save you time if you are revising many documents.

💡
Note that E1 will auto-suggest based on file names so it is useful to keep your file names consistent on your computer prior to upload.
  • Select the 'Auto Suggest Revisions' button
  • You will get a pop-up which will outline the recommendations of which new document should supersede an old document
  • Use the 'Correct?'  column to select 'Yes' or 'No' next to each document. Check every document.
  • Select 'OK'
article image

Manually confirm revisions

If you would prefer to manually confirm, you can do this for all documents. Alternatively you can use auto-suggest to confirm correct auto-suggestions, and manually confirm the incorrect suggestions after.

  • 'Select' next to the relevant document you would like to manually confirm the revision for
  • A pop-up will show and will recommend a document to supersede - you may select this here if it is the correct document
  • If it is not the correct document, use the search box to find the file you require and 'Select' next to it

Once complete, you will see the new document in the table with the new file name, showing the document which was been superseded, a new revision version, as well as the Addendum name.

You can 'Undo' from here if an error is made.

article image

Confirm Packages

  • Once you have finished uploading revised documents, select 'Next Step: Document Matrix'
  • Ensure your packages are up-to-date - you can amend them here if you need to. Find out how here.
  • When you are finished, select 'Finalise Packages' then 'Confirm Changes'

Notify Subcontractors

You will not need to do this step if you have not issued any enquiries to subcontractors in the Trade whose packages you have updated.

However, if you have already invited subcontractors to these packages in the Procurement phase and you make changes to documents in their packages, you will be prompted to notify them.

  • A pop-up will appear to Confirm & Notify. The subcontractors that you need to notify will be auto-selected.
  • Input a Subject and Message to Subcontractors if you wish, then select 'Complete Addendum'
  • The subcontractor will be notified by email that they need to download the latest set of documents

article image

You can view a record of the revisions applicable to each subcontractor you have by accessing the Audit Trail within the Package Dashboard.

  • Navigate to the Package Dashboard by selecting the relevant package from the Schedule
  • Select the three dots on the far right on the same line as the relevant subcontractor
  • Select 'View Audit Trail'

article image
Did this answer your question?